cemento ranang 300k apil sa leveling sa yuta..bcng kuwang pa
think of it this way:
1. kelangan kag architect or contractor diba so that ur house will be approved na inhabitable, di raman ikaw ang mgbuot2 ug himog balay ana, kelangan kag permit to build or operate from the city.
2. how soon would u want to finish your house? kung eputol2 man gud nimu, madaot na imung mga materials daku ang tendency di mahuman ang bay
3. with the length of time u want to finish your house, that entails hiring the number of people to finish it, ryt? let's say (1) 5 kabuok laborer working 6 days a week nya swelduhan baya na nimug at least P150 each per day. di ra laborer imung kelangan, naa panay tig (2) measure2, (3) naa pud mason, (4) tig semento, (5) tig pintal, (6) electrician para sa mga wiring, (7) plumber or tubero for ur pipe structure and much more.
4. materials: this entails 50-60% guro sa imung gasto to build a house. (1) cement; (2) sand and gravel pgpatag sa imung yuta OR to fill up weak foundations in the ground; (3) scaffolding (erent ni nimu ky 2 storeys man kaha ang balay -- either puthaw or bamboo scaffolding); (4) water; (5) electricity for the operation of machinery (drills, cement mixers, suga, etc); (6) glass for your windows; (7) lumber (di man pud cemento tanan ang balay); (
tiles (hala kani ky per square feet raba ni); (9) fixtures (lababo, shower or gripo, toilet bowl); (10) hollow blocks; (11) steel bars for ur posts pud (panganvas mong mga materials ug laing butang sa hardwares -- makalibat gyud)
5. your time (imu na emonitor personally ang pgbuild dili kay once a week ra nimu echeck ky ikaw ray alkansi ana ky imung materiales pwede mailisan ug barat quality materials, pwede pud madaot inig uwan)
6. damages (in terms of transporting your materials, naa man gyuy mabali, mabuak, madaot..be ready for that gyud)