d ba sa pag-ibig, by phasing man na ila basehan sa pagpa loan ug house construction?
start ka sa fence, then poste. then loan ka, roll nimo ang kwarta.
daghan man nakabuhat ana.
ayaw lang jud mo ana mga row house. ses, minilyon. tagaktak. ajinomoto
late na ni nga updates
week 13
beam reabs are complete. plywood shuttering starts on the beam and slab. the progress was slow due to rains. kng mguwan they have to find shelter pra dli mbasa then go back to work once wla na uwan. i told them be very extra careful coz its slippery. wla bya ta insurance.
front view
week 14
shuttering done
slab rebar layout is almost complete. the preparation for the slab pour is ready. the stairs for the upper floor where the chain gang tranports the buckets of concrete is already waiting.
i thought it was just a simple stairs but when i arrived at the site nshock ko sa kadaghan sa kahoy nga nagamit. it would been used to brace the scaffolding and i think naa pa unta sobra nga kahoy. pro its better safe than sorry coz dnha cla mg.agi ang mga tao.
rebars on one of the rooms
view from the masters with neighbor's cow at the back, bathroom is lowered 2 inches pra dli msulod ang basa sa master bedroom.
the rebars fabrication station
German, one of our assistants carries buckets of water to wash the forms for concrete pouring. look how much wood consumed for the stairs alone. pwerting daghana.
Last edited by reypel; 08-11-2011 at 11:17 AM.
wow nice bro...ig blessing hap ayaw kalimot hahaha...
Week 15 (Pouring of concrete)
We started early at 730am after they had breakfast. we hired 20 additional laborers to help us with the pour. plus 6 existing workers and myself so we are 27 all in all. the weather was fine but there were rain clouds so it was expected to have rainshowers. it did rain after lunch but thank God it was not a heavy down pour. the 27 man-team worked from shine to rain to shine again. i thought i could spend 5 hours OT on the pour but we did it in less than 8 hours with the help of some energy drinks( sting & cobra, i hope ill get something by endorsing these hehe). we connected lights in case it'll get dark but wla man magamit.
the chain gang at work
2 hours after the job we are already a quarter of the total progress. it must have been the result of the energy drinks.hehehe pagmayroon ka nito wla kang talo!
During the break, we connected tarps near the mixer in case it'll rain. pero niuwan gyud.
after 7 hours the chain gang is done with job and 2 of the men does the finishing touches
Smile Tinoy smile!
Tinoy of the panday does the brooming of the slab.
Thank God it was done without any hassles.
asa ni dapit brad sa bogo? pila na gastto ana ron?